What we know about Meta

What it is

Meta's first Canadian data centre, in Sturgeon County north of Edmonton. Meta puts the investment at more than CA$13 billion and the facility at about one gigawatt. Ground has been broken, which makes it the clearest example on this site of a project that is real and building rather than announced.

Why it matters for the grid

It is one of exactly two projects holding a piece of the grid operator's 1,200 MW interim large-load allocation through 2028. In other words, it is not just permitted, it has a connection — which most of the queue does not.

The jobs, attributed

Meta and the Government of Alberta say the project means more than 3,000 construction workers at peak and more than 300 permanent jobs. The province separately estimates roughly $250 million a year in benefits to Albertans, through royalties, taxes, levies and transmission fees; Meta's own announcement gives no revenue figure. These are their figures, and we report them as theirs, not as independently verified.